Owner engineering/site supervision
General Duties
Supervising
/ Owner Engineering the whole activities of the EPC work of a utility-scale
solar PV station (30 MWp) including all engineering aspects (Civil, Electrical,
Mechanical)
Activities:
All project activities including:
· Management
· Budget and schedule management
· Document control
· Handling and reviewing contracts
· Supervising Installation and commissioning
· Reporting
· Ensuring all energy efficiency measures are
implemented in all aspects
of the projects including all equipment and
all operational activities
· QC/QA
· HSE, Risk mitigation
Specific contractual duties for this project includes:
1. Hold regular project control and progress
meetings with the EPC contractor which may include:
·
Logistic/organizational meetings to review the proposed
staffing from the EPC contractor and its sub-contractors, review the main
components delivery plan at the Site (above all during construction activities
in adjacent sites and/or in view of possible delays in shipment of components);
·
Technical meetings to discuss unexpected issues encountered
during the construction;
·
Site progress/review meetings;
·
QHSE meetings;
·
Meetings during commissioning and Provisional Acceptance
tests; and
·
Other meetings at the Site and/or at the DNV GL office in
Dubai as required by the
·
Customer.
·
Interact with insurance advisor
2. Reviewing the design and documentation
provided by the EPC contractor, commenting on technical aspects of the design
including but not limited to the suitability, quality and fitness for purpose
of the works proposed by such design and documentation;
3. Inspecting the quality and specification of
items delivered to site, as far as reasonable, prior to their installation;
4. Review the EPC contractor’s proposed project
management system and monitor its
correct application;
5. Ensure that the Environmental and Social
Management Plan (“ESMP”) and IFC performance standards from PS1-PS4 are
correctly implemented and maintained during the construction, commissioning and
operation (for the first two years) of the Project. The subcontractor shall
review the system adopted by the EPC contractor to keep track of the actions
undertaken to comply with the ESMP and any possible deviation from the requirements
of the plan;
6. Review the working practices adopted by the
EPC contractor and its sub-contractors,
including how the works from different teams
are organized and harmonized to ensure the achievement of the requested level
of quality, health and safety;
7. Assist the Project Owner providing technical
support in analyzing and verifying claims of the EPC contractor or insurance
claims. The technical support can include review of technical report or
drawings from the EPC contractor and meetings with the Customer and EPC
contractor
Specific duties with respect to civil works:
·
Provide all the necessary on-site project supervision and monitoring;
·
Monitor the setting out of the site foundations and all other
civil works to ensure compliance with the EPC contract, project consents and
other technical requirements applicable;
·
Review and monitor the execution of the contractor’s quality
plan and quality control procedures and regimes.
Specific duties with respect to electrical
works:
·
Provide necessary on-site project monitoring including
factory acceptance tests (based on documents) on electrical components;
·
Review protection requirements and verify that the EPC
contractor ensures that the appropriate equipment is procured and installed in
accordance with these requirements;
·
Ensure that the contractor progresses the design and
implementation of the site electrical infrastructure works and monitor the
design, manufacture, delivery, installation and commissioning of the
infrastructure by the contractor in accordance with the requirements of the
contract specifications including factory acceptance testing as necessary;
·
Review and monitor the execution of the contractor’s quality
plan and quality control procedures concerning the electrical works.
Review the draft switching schedules, electrical operating procedures and site
safety rules for commissioning and subsequent operation of the Project for
approval, adoption and implementation by the Customer;
·
Review and monitor the commissioning program and procedures,
safety procedures and controls before energization of the site electrical infrastructure
and the PV modules;
·
Monitor liaison between the EPC contractor and Customer about acceptance of the on-site connection and substation and coordinate
the interface between the contractor and the Customer up until the expiry of
the term of the contract.
Specific duties concerning PV modules:
·
Monitor the progress of the EPC contractor to ensure that the
PV modules are delivered, installed and commissioned in accordance with the EPC
contract;
·
Witnessing, overseeing and reporting to the Customer on the
construction, installation, testing and commissioning of the Project;
·
Undertake a high-level visual inspection of a sample of PV
modules immediately before energization to determine as far as reasonably practicable
its fitness for energization and report to the Customer and the contractor any
outstanding works, defects or deficiencies and progress completion of remedial
works as necessary;
·
Due to the large number of PV modules to be installed, select
a representative sample of modules for a visual inspection (50%), and the review
of the flash tests for all the PV modules supplied to the projects;
·
Ensure the SCADA is fully functional and accessible from
remote locations;
·
Review performance tests (carried out in the factory)
certificates.